Boeing
Revises 787 First Flight and Delivery Plans; Adds Schedule Margin
to Reduce Risk of Further Delays
First flight moved into fourth-quarter 2008; deliveries
to begin third-quarter 2009
Production plan now targets approximately 25 787
deliveries in 2009
Company expresses confidence in plans; will work closely with
customers to minimize disruption
No change to 2008 earnings guidance; strong 2009 EPS growth still
expected
EVERETT,
Wash., April 09, 2008 -- Boeing [NYSE: BA] today announced a revised
plan for first flight and initial deliveries of the 787 Dreamliner
that includes additional schedule margin to reduce risk of further
delays on the program.
While
significant progress has been made assembling Airplane #1, first
flight is being rescheduled due to slower than expected completion
of work that traveled from supplier facilities into Boeing's final
assembly line, unanticipated rework, and the addition of margin
into the testing schedule. The new delivery schedule is based on
a more conservative production plan developed with the 787 partner
team. That schedule now targets approximately 25 deliveries in 2009.
First flight of the all-new airplane will move into the fourth quarter
of this year rather than the end of the second quarter, and first
delivery is now planned for the third quarter of 2009 instead of
first quarter.
Company
officials expressed confidence in the new plan and the steps being
taken to accelerate program performance.
"Over
the past few months, we have taken strong actions to confront and
overcome start-up issues on the program, and we have made solid
progress," said Boeing Commercial Airplanes President and CEO Scott
Carson. "Nevertheless, the traveled work situation and some unanticipated
rework have prevented us from hitting the milestones we laid out
in January. Our revised schedule is built upon an achievable, high-confidence
plan for getting us to our power-on and first-flight milestones.
Also, while the fundamental technologies and design of the 787 remain
sound, we have inserted some additional schedule margin for dealing
with other issues we may uncover in testing prior to first flight
and in the flight test program."
The
company said in January it would be conducting a comprehensive assessment
of its supply chain and production system capabilities to determine
the details of the 787's flight test program and initial delivery
profile. As a result of that assessment, the first-year delivery
plan announced today will be followed by a more gradual ramp up
to full-rate production than previously planned.
"We
deeply regret the disruption and disappointment these changes will
cause for our customers, and we will work closely with each of them
to minimize the impact," said Carson. "We have taken significant
action to improve supply chain and production system performance,
such as our investment in Global Aeronautica, but based on our assessment,
the prudent course is to proceed with a more gradual ramp up to
full-rate production."
Pat
Shanahan, 787 vice president and program manager, echoed Carson's
comments about the progress being made in 787 factories.
"The
work that remains to be done on Airplane #1 is well defined, and
we can see our way to -- and have confidence in -- the new milestones
we have set for it," said Shanahan. "We have addressed the major
challenges that slowed our progress while trying to complete the
primary structure -- the parts shortages, engineering changes, and
manufacturing changes -- and we are well into the systems installation
that is the precursor to putting power on the airplane for the first
time. We have also worked closely with our partners to achieve higher
levels of completion of their parts of subsequent airplanes, and
we will continue to drive improvements in the supply chain and production
system performance," he said.
For
tracking program progress, Shanahan outlined a series of milestones
that will occur before June 30: 787 static and fatigue structural
test airplanes will move to their testing locations; Airplanes #3
and #4 will enter final assembly; hardware airworthiness qualifications
will be complete; and power on will be achieved.
Shanahan
also said the program has changed the timing of the introduction
of two 787 derivatives. The 787-9, a larger variant of the airplane,
will be the first derivative of the baseline 787 with delivery planned
for early 2012. The 787-3, a shorter-range model previously slated
to deliver in 2010, will now become the second derivative of the
airplane family.
While
research and development costs will likely increase as a result
of the 787 schedule change, Boeing expects no change to 2008 earnings
guidance. The company continues to expect strong earnings per share
growth in 2009 and will provide complete 2009 financial guidance
when it holds its first-quarter 2008 earnings conference call later
this month. The outlook for the company's defense business and in-production
commercial airplane programs remains strong.
Boeing
held a conference call with Scott Carson and Pat Shanahan to discuss
the 787 program today at 11:00 a.m. EDT, 8:00 a.m., PDT.
References:
Boeing
News
|